FCA Enforcement data 2024/25, what does this tell us in terms of enforcement trends?
了解更多
Civil Justice Council publishes final report into review of litigation funding – what does it mean for litigants, practitioners and funders?
了解更多
It is, to say the least, unusual for a £1,560 claim to reach the Supreme Court but it did so in Armstead v Royal & Sun Alliance Insurance Company Ltd [2024] UKSC 6. The case raises a fundamental question in applying the tort of negligence, where economic loss arising from a contractual liability to pay a sum of money, results from physical damage to property.
The claimant, Ms Armistead was involved in two separate road collisions within a short period of time, neither of which were her fault. After the first collision, and while her car was being repaired, she hired a car from a company called Helphire on terms that it would seek to recover the cost from the other driver's insurers and would only look to her for payment if that claim failed (the "Hire Car").
The hire agreement between Helphire and Ms Armistead was on Helphire's standard terms and included an obligation to return the Hire Car in the same condition as it was as at the start of the hire and to indemnify Helphire for any damage to the Hire Car. Clause 16 of the hire agreement stated:
"You will on demand pay to [Helphire] an amount equal to the daily rental rate specified overleaf, up to a maximum of 30 days in respect of damages for loss of use for each calendar day or part of a calendar day when the vehicle is unavailable to Helphire for hire business because … the Hire Vehicle has been damaged".
Less than two weeks later, another vehicle, a Ford transit van, collided with the Hire Car. Although the Hire Car was damaged, Ms Armistead was able to carry on driving it. She returned it when the repairs to her own car had been completed. It then took 12 days to complete the repairs to the Hire Car. Helphire made a demand on Ms Armistead under clause 16 of the hire agreement for the rental charge for this period, amounting to £1,560 (the "Clause 16 Sum").
Ms Armistead brought proceedings against the van driver's insurers, Royal & Sun Alliance Insurance Company plc ("RSA"). The remedy claimed was the cost of the repairs and the Clause 16 Sum. RSA defended the proceedings on a number of bases including that clause 16 was an unfair term and/or unenforceable and/or a penalty and that Ms Armistead had failed to mitigate her loss by refusing to pay the Clause 16 Sum to Helphire.
At trial, the Judge dismissed Ms Armistead's claim for the Clause 16 Sum on the basis that it was irrecoverable economic loss. He did not express a view on whether clause 16 was unfair, unenforceable or a penalty. Ms Armistead appealed but that appeal before Recorder John Benson QC was dismissed on the same (and different) grounds.
Ms Armistead appealed to the Court of Appeal. Again, her appeal was dismissed for several reasons, again including that the Clause 16 Sum was irrecoverable economic loss.
The matter came before the Supreme Court. It approached the case by applying three established principles:
The Supreme Court held that there was no reason in principle why recoverable loss should not include a contractual liability to a third party provided that the liability is consequential on physical damage to a claimant's property.
The key issue was one of remoteness. As to that, the Supreme Court stated the following:
The Supreme Court determined that once the claimant has proved that a tort has been committed and that the loss claimed was in fact caused by the defendant's breach of duty, it is for the defendant to assert and prove that the damages claimed should be limited in some way. In the case before it, RSA had not pleaded a case that the Clause 16 Sum was not a reasonable pre-estimate of Helphire's loss of use and had consequently adduced no evidence on the point.
In the circumstances, Ms Armistead's appeal succeeded and RSA was found liable to pay damages in respect of the Clause 16 Sum.
As it had been raised in submissions, the Supreme Court went on to consider what the position would be if the pre-estimate of loss was found not to be a reasonable sum. Drawing from authorities involving claims for breach of contract, the Supreme Court stated its view, obiter, that Ms Armistead would, in this situation, be entitled to recover as damages such lesser sum as would represent Helphire's reasonably foreseeable loss of use.