Drugmakers fined in Turkey over no-poach agreement and information sharing
Find out more
In Kajima Construction Europe (UK) Ltd & Anor v Children's Ark Partnership Ltd [2023] EWCA Civ 292, the Court of Appeal clarified:
Executive summary
In order to ensure a contractually agreed dispute resolution procedure is enforceable, the procedure should be as unambiguous and precise as possible, and clearly state:
If the procedure requires a form of third party adjudication, careful consideration should be had to ensure that the parties to a potential dispute are able to be represented and to participate in that adjudication fairly.
If a party issues proceedings in breach of a dispute resolution procedure, the usual approach is for the Court to stay the claim. However, this will turn upon the facts of each case.
Any contracting party seeking to agree a bespoke dispute resolution procedure should consider carefully (a) what it wants that procedure to be, and (b) whether that desired procedure is adequately described as a matter of contractual drafting. When drafting significant contracts or contractual arrangements involving more than two parties, parties should take advice from dispute resolution counsel as part of their use of external counsel.
Once in a dispute, a party should consider carefully any bespoke dispute resolution provisions, and take advice on how to make best use of those provisions in order to resolve the dispute.
In 2004, Brighton and Sussex University Hospital NHS Trust (the "Trust") engaged Children’s Ark Partnership Limited ("CAP") to redevelop one of its hospitals (the "Head Contract"). CAP subcontracted with Kajima Construction Europe (UK) Limited ("Kajima") (the "Sub-Contract"). Kajima Europe Limited guaranteed Kajima's obligations under the Sub-Contract.
The Head Contract established a Liaison Committee with representatives from the Trust and CAP. The dispute resolution procedure (the "DRP") in the Head Contract stated that:
CAP and Kajima imported the material terms of the DRP into their Sub-Contract.
Following the Grenfell disaster in 2017, a dispute arose between CAP and Kajima as to certain remedial works needed to the hospital. CAP and Kajima agreed a standstill agreement and series of extensions for Kajima to perform the work. When Kajima refused to agree a further extension, CAP issued proceedings on the basis that there was not sufficient time to engage the Liaison Committee pursuant to the DRP before the limitation period ran out.
CAP applied to stay the proceedings, pending compliance with DRP. Kajima applied to strike out the proceedings, on the basis that they had been issued in breach of the DRP.
The Judge at first instance ruled, amongst other things, that the DRP was unenforceable. Even if it was enforceable, the Judge would have ordered the proceedings be stayed, not struck-out. Kajima appealed.
In his judgment, Lord Justice Coulson ruled that the DRP was unenforceable for uncertainty for the following reasons:
Lord Justice Popplewell, also presiding over the case, agreed with Lord Justice Coulson that the DRP was unenforceable, but stated that the DRP was only unenforceable because the DRP did not state when the process was concluded, and that he was prepared to overlook the other issues that arose from the "clumsy" adoption of the DRP into the Sub-Contract. He was also inclined to agree with Kajima's alternative argument that only commencing the DRP was a prerequisite to litigation (and not participation in the process thereafter) and that such a requirement was enforceable. However, this argument was not admissible in the appeal and so it was not open for Kajima to argue it.
The remaining Court of Appeal Judge presiding over the proceedings, Lord Justice Holroyde, agreed with Lord Justice Coulson's reasoning.
The Court of Appeal ruled that a stay will be the usual remedy that the Court will grant in these circumstances, although each case will depend on the facts. Based on the relevant authorities a stay was the correct remedy in this case, even though it would deprive Kajima of a limitation defence.
Lord Justice Popplewell agreed, but clarified that if the condition precedent to litigation under the DRP was only to initiate the DRP (had that argument been open to Kajima, as above), then it would be appropriate to strike-out the claim.